Even as India's Parliament is waiting to debate (or not!) the newly-proposed National Green Tribunal Bill, the High Court of Delhi has yet again served a judgement that can put to shame the regulatory responsibility of the Ministry of Environment and Forests (MoEF). Dated 26 November 2009, the reasoned 36-page set of contentions has also brought to light yet again the spineless functioning of the National Environment Appellate Authority (NEAA) (see here and here). It may be borne in mind that it is this NEAA that the National Green Tribunal (NGT) seeks to replace.
But for now, here is the story behind my strong statements above. On 26 July 2007, MoEF officials stamped a clearance for Panduranga Timblo Industries for the renewal of a mining lease for the production of 200,000 tonnes per annum (TPA) of iron ore at Rivona village in South Goa. The two mines covered by this new lease had earlier been functional from 1980 to 1994, digging out iron, manganese and ferro manganes. Thereafter, until 2006, the mines were not in use. But with an revival of interest for such ore in China, Korea and Japan, the mine owner applied for a renewal of the lease.
At the same time Pandurang Timblo applied to the MoEF for environment clearance. This is mandatory for any mining operation over 5 hectares, and a standard procedure to obtain such clearance is prescribed under the Environment Impact Assessment (EIA) notification, 2006. This includes preparation of an EIA report, holding public hearings in the project area, and scrutiny by an Expert Appraisal Committee (EAC). These steps were gone through, and the approval was given.
100 per cent opposition
However, Utkarsh Mandal, a farmers' society in South Goa filed a case before the NEAA claiming that there were irregularities in the approval given by the EAC. The NEAA, established in 1997, is the designated authority before which any grant of environment clearance can be challenged. The case was heard by a 3-member panel without a Chairman or Vice Chairman of the authority being present (the NEAA has never held a full-member review of challenges; it has been under-staffed from its inception). The three members - J C Kala, K Prasad, and I V Manivanan - gave their verdict on 14 October 2008, dismissing Utkarsh Mandal's appeal.
Utkarsh Mandal's appeal, argued by two Delhi-based pro-bono lawyers, Ritwick Dutta and Rahul Chaudhry contained the following grounds:
-
While the notice for the mandatory public hearing was issued 30 days prior to the date of hearing (as required by law), the Executive Summary of the EIA report was received by the Gram Panchayat of Rivona only nine days prior to the hearing, giving the villagers insufficient time to examine the proposed renewal of the mining lease.
-
The Goa Pollution Control Board (GPCB) organised as many as 14 public hearings in the same advertisement in Indian Express. Of this, public hearings for five proposed mines were scheduled on the same day (31 July 2009), venue and time as the hearing for the Borga Iron Ore mines. While there may be some administrative convenience in having a single venue (in this case, Vithal Niketan, Vithal Devasthan, Sangauem), each hearing throws up significant and serious issues, often requiring a whole day by itself. Combining the hearings, whether in issuing advertisements or actually holding the consultations, treats a very serious process as a mere administrative formality.
-
The minutes of the public hearing showed that out of the 237 members present at the hearing, 67 made written submissions, and "Not a single application nor a single member of the public was in favour of restarting of the mine due to [concerns of] grave environmental and social damage." How was it, the petitioners asked, that the EAC granted approval, disregarding the fact that there as 100 per cent opposition to the project at the public hearing?
The minutes of the EAC meetings have only a passing reference to the public hearing on the said project.
Study the impacts first
Exempt, but not exempt
Red flags over green tribunal
Innovative interpretations
Ironically, when the case was heard before the NEAA, innovative interpretations and responses appeared, all of which were recorded in the NEAA order of 14 October 2008.
The NEAA first declared that the EIA largely covered "all the critical aspects of mining project" and therefore the contention of the appellant could not be upheld. The authority also did not agree with the claim that the mining activity would be damaging environmentally as well as socially. According to the NEAA, adequate safegaurds and conditions in the clearance letter could ensure this. But who is to enlighten the NEAA of the dismal state of monitoring companies' compliance with environment clearance conditions? There are six regional offices of the MoEF, with 2-3 officials in each to monitor over 6000 projects (see: this link.)
If that's incredible, it is simply shocking to observe how the NEAA dealt with the next point. The petitioners claimed that the EIA should have been made available to the local panchayat one month before the date of hearing. The NEAA, however, did not see it this way. Instead, the NEAA upheld Pandurang Timblo's response - that only the notice of the project hearing needs to be issued a month in advance, and this notice needs to say where the documents pertaining to the hearing would be made available, but the documents themselves need not be available on that date!
About the 100 per cent objection to the mine from locals, Pandurang Timble countered that by pointing to a dated 9 September 2007 written to the District Collector of South Goa by 57 persons from Rivona and neighbouring villages, supporting the proposed restarting of the mines. The company also argued that there were 9 other mines in the area, which the locals were not objecting to. This, it claimed, showed that the locals' opposition was malafide.
On to the High Court
When their appeal before the NEAA was dismissed, Utkarsh Mandal took its case to the Delhi High Court. And here, the appellants were armed with some new strength. During an appeal before the High Court, the applicant is allowed to file additional information. Very interestingly, through a Right to Information application a critical conflict of interest was revealed.
M L Majumdar, the Chairman of the EAC which approved the proposal from Pandurang Timblo, is a retired 1966 batch IAS officer. It was revealed that at the time of grant of clearance to PT, he was himself a Director of four mining companies namely, Uranium Corporation of India Limited, R B G Minerals Industries Limited, Hindustan Dorr-Oliver Limited and Adhunik Metaliks Limited. Justice S Murlidhar of the Delhi High Court took serious view of this. But A S Chandhiok, the Additional Solicitor General, appearing for the ministry, said Majumdar's stake in the mining sector should not matter, since he was only one of the members of the EAC, and the decision of the majority would anyway prevail.
Justice Muralidhar didn't agree. The High Court's judgment cites several administrative case laws and judgements of the Supreme Court. When it comes to the Utkarsh Mandal case, it noted that 'procedural impropriety' could be grounds for reversal of a judgment, as in the decision of the Supreme Court in Tata Cellular Co. v. Union of India (1994) 3 SCC 651 (SCC, at p. 677-78). While the entire judgment is welcome, a few points are particularly noteworthy, for their larger relevance:
-
The first is with reference to the availability of the executive summary of the EIA only nine days prior to the public hearing. The High Court's judgement rejected the NEAA's limited interpretation. It states that public hearings under the EIA notificaiton, 2006 are public acts of the central government. Therefore, "the opportunity to participate and voice an opinion on the project has to be a meaningful one. It can be rendered ineffective by not insisting that the Executive Summary should also be made available 30 days in advance of the public hearing."
-
Second is the issue of application of mind by the EAC members in according a decision. Referring to a vast array of case law that defines appraisal and the role of a committee like the EAC, the Court held that the EAC should have considered all the points raised at the public hearing and only then taken a decision on the project. To the contrary, the minutes of the EAC meetings have only a passing reference to the public hearing on the said project.
-
Third, while referring to the six public hearings in one day, the judgement states its concern that the requirement on the public hearing is taken "so lightly by the MoEF. This needs immediate correction. If the hearing has to have adequate publicity then the notices would have to be repeated and spread over a period of ten days so that as many people as possible are made aware of such public hearing." By multiple hearings at the same time and venue reduces public hearings to becoming an empty formality.
The judgment also commented upon the rush to clear projects by the MoEF. On this Justice Muralidhar states, that "the unseemly rush to grant environmental clearances for several mining projects in a single day should not be at the cost of environment itself. The spirit of the EAC has to be respected. We do not see how more than five applications for EIA clearance can be taken up for consideration at a single meeting of the EAC. This is another matter which deserves serious consideration at the hands of MoEF."
With this and other sound reasoning the court "kept aside" the environment clearance granted and invoked a cost of Rs.10,000 on each of respondents which they have to pay to Utkarsh Mandal.
But is this truly an era of change, or simply an pleasant abberation? An order like this can kindle some hope. The sensitivity and regard that a regulatory system ought to embibe has had to be stated obviously through such written committment. Which is why the question about the NGT in the opening paragraphs. Is setting up a new institution with bleaker mandate than the NEAA a solution to the problem like the cases above, when the problem bears the mask of political thinking?